- Week of April 20th--slab--it went in today which is April 22nd
- Week of April 27th--walls
- End of May--under roof
- End of June--electrical
- Construction completion--end of September
- Close--probably early November based on neighbors' remarks that it is taking about 5 weeks from construction completion to occupancy certificates.